Sunday, 11 April 2010

Catching Up

It's been a while since we updated the blog and a lot has happened. We have now moved into Halfway House and have settled in. It only took a week to unpack the boxes and put our things out around us. We haven’t unpacked everything as a) I don’t think there would be room and b) with moving again in a (hopefully fairly) short space of time we didn’t see the point, so a lot is still packed and in boxes in the spare room. We can see The Garden House from the back windows so it keeps us motivated!

Darran has been off the last couple of weeks and has made great progress. The plumbing is now completed (just the shower valves to fit) and he has also fitted the manifold to the under floor heating pipes so we no longer have spaghetti to contend with. We have tested the hot and cold water pipes and no leaks!




We now have the raised vegetable beds in, filled and planted.



The main objective continues to be the bricking. Hopefully as we’re now moving into the nicer weather we will be able to get on with it in the evenings. Darran has done some over the last couple of days as the weather has been so nice. He has done the back of the garage and around under the breezeway, ready to point.



Sunday, 7 March 2010

On The Plinth

Yesterday we stuck the blue bricks on top of the plinth around the garage.



That was followed by a trip into town on the hunt for an oven for Halfway House as it doesn't have one. We were unsuccessful with the oven, but did get three soil pipes, a sack truck and the three toilets we wanted as they were on a half price offer and we were also given a further 10% off!

Monday, 1 March 2010

Still Soldering On

It's a month to the day since we last did an update. This hasn't been because we have been slacking off, it's just that what we've been doing has been pretty much the same for the last month - plumbing!

The hot and cold water loops are complete on the bedroom wing which is the most complex as it has the bathroom and ensuite. Now over to the living area and kitchen and cloakroom, and then across to the utility room. It has all gone really well and Darran has done a great job considering he hasn't ever done this kind of thing before.

The soldering of the joints has gone to plan. The real proof will be in the pressure test. No fires with the blow torch either, not even small ones (other than a slight charring of the flux brush)!





In other news, we now have electricity in the house which is a big tick. We have an isolator switch in the garage which is connected to the meter and have laid armoured cable (or ****** armoured cable as it was known pretty soon after we realised how difficult it is to do anything with) across the breezeway and into the lobby area to a consumer unit. We can now get on with the electrics when the plumbing has been completed.

Monday, 1 February 2010

Plumbing And A Halfway House

Too cold for bricking, this weekend saw a big leap ahead with the plumbing. The hot water loop is complete and the cold water loop is almost there.

These pipes are currently cut to size, bent to the correct angle and set in place ready to be clipped to the joists and the joints to be soldered.


After weeks of debate about copper v plastic pipe work (and yes, we mean weeks and weeks), copper was decided. It's going well so far, Darran's 'pipe-benders-face' is now easily recognisable, I think the 22mm pipe is harder to bend than first thought.

In other news, we have found a property to rent where the wall at the end of the little courtyard garden is the same wall that surrounds our plot. It is a perfect location. I have dropped the application form off today, so hopefully we'll be successful and be able to take the tenancy from the 1st March which will give us a few weeks to move in while we still have our Oxfordshire place. We'll be so glad to have moved and being so much closer will make such a difference.

Saturday, 23 January 2010

Hi Ho Hi Ho It's Back To Work We Go!

It was back to work for us this weekend after a long Christmas and New Year break. We had intended not to work over Christmas as we both needed a break and to do some research and planning for the next stages. The weather also meant that for a couple of weekends we were stuck due to the snow.

Today we pointed some more brickwork around the garage plinth and took delivery of the copper pipes and fittings to start the plumbing. We also decided where our raised vegetable beds are going to go and will be marking those out tomorrow. I can't wait to get growing!

In other news, we had our defects inspection for the slab and drainage a few weeks ago. A percentage of the total cost of this stage of works was retained until six months after completion of the stage, when another inspection takes place and any mistakes/problems that have crept up are either rectified, or the outstanding balance is reduced accordingly. We have had a problem with the drains, as they are set too close to the slab and we can't get bricks, and sometimes not even the backer panel for the bricks, in behind the drains and the block work. The architects are now contacting the contractor to see whether they want to come and dig up the drains, chop a bit out and reset, or they reduce their balance. Secretly hoping for a bit of both, but I think it will be one or the other!